Description: # JIRA Agile Metrics
        
        A tool to extract Agile metrics and charts from JIRA projects.
        
        ## Installation
        
        Requires Python 3.6 or later.
        
        Install Python 3 and the `pip` package manager. Then run:
        
            $ pip install jira-agile-metrics
        
        You can do this globally, but you may want to use a virtual Python environment
        (`venv`) instead to keep things self-contained.
        
        See [The Hitchhiker's Guide to Python](http://python-guide.org/en/latest/) for
        the full details about how to install Python and venvs.
        
        This should install a binary called `jira-agile-metrics` in the relevant `bin`
        directory. You can test it using:
        
            $ jira-agile-metrics --help
        
        ... which should print a help message.
        
        ### Using Docker
        
        If you prefer, you can use [Docker](http://docker.com) to install and run
        `jira-agile-metrics` with all the relevant dependencies in place. After
        installing Docker, run:
        
            $ docker run -it --rm -v $PWD:/data optilude/jira-agile-metrics:latest config.yml
        
        This will run `jira-agile-metrics` with the configuration file `config.yml` from
        the current directory, writing outputs also to the current directory. The
        argument `-v $PWD:/data` mounts the `/data` volume, where output files will be
        written, to the current working directory. You can of course specify a
        different bind mount.
        
        ### Using Docker in batch mode
        
        There is a second Docker image, which can be used to run multiple config files
        in batch mode, for example to generate metrics overnight.
        
        To use it, create a directory containing one or more configuration files, with
        the extension `.yml` or `.yaml`, and a _different_ directory for the outputs.
        Assuming these are `/path/to/config` and `/path/to/output`, you can run
        the following Docker command periodically, e.g. using `cron` or another
        scheduler:
        
            $ docker run --rm -v /path/to/config:/config -v /path/to/output:/data optilude/jira-agile-metrics:batch-latest
        
        When this is finished, you should see a directory under the `output` directory
        for each of the config files in the `config` directory, containing the reports
        and charts. You will also find a file called `metrics.log` containing the log
        output during the run, which may be helpful in diagnosing any problems.
        
        Any command line arguments passed to `docker run` after the image name will be
        passed directly to `jira-agile-metrics`. So, for example, if you wanted to use
        the `-n` option to limit the number of results fetched from JIRA (for testing
        purposes), you can pass `-n 10` (or some different number) at the end of the
        command line above.
        
        ## Usage
        
        The basic usage pattern is to run `jira-agile-metrics` with a configuration
        file, written in YAML format (see below), which describes:
        
        - how to connect to a remote JIRA instance (this can also be set using command
          line options);
        - what metrics (spreadsheet-like data files, charts as images) to output;
        - various settings used to calculate those metrics; and
        - a description of the stages of the workflow the relevant JIRA tickets go
          through.
        
        The tool will then connect to JIRA using its web services API, run a query to
        the relevant tickets and their history, and calculate the requierd metrics.
        
        The outputs are written to local filesystem files. Data files can be written in
        CSV, XLSX or JSON formats (depending on the extension of the desired output
        file), whilst charts are written as PNG images.
        
        ### Server mode
        
        `jira-agile-metrics` comes with a simple web server that can be used to produce
        metrics by uploading a configuration file and downloading a ZIP file with data
        and charts. To start it, run:
        
            $ jira-agile-metrics --server 5000
        
        This will start a server on port `5000` (you can also specify a bind host name
        or IP address, e.g. `0.0.0.0:5000`). Visit this address in a web browser and
        upload a file.
        
        In this mode, all other command line options are ignored.
        
        **Note:** The web server is designed for low-volume usage only, and does not
        have a sophisticated security model. It is simply a more accessible front end
        to the features of the command line tool. The server will wait, synchronously,
        whilst JIRA is queried and charts are produced, which can take a long time.
        During this time, the browser will wait, and threads will block.
        
        **Warning:** The web server does not encrypt requests, which means that by
        default JIRA credentials are transmitted in plain-text. You are strongly adviced
        to configure a reverse proxy (e.g. `nginx`) with SSL enabled in front of it.
        
        #### Using Docker to run the web server
        
        There is a separate Docker image for running the web server, which uses `nginx`
        and `uwsgi` for improved performance and stability (but still not SSL, which
        would need to be configured with a domain-specific certificate):
        
            $ docker run -d --rm -p 8080:80 --name jira_metrics optilude/jira-agile-metrics:server-latest
        
        This will run the server in daemon mode and bind it to port `8080` on the local
        host. To stop it, run:
        
            $ docker stop jira_metrics
        
        See the [Docker documentation](https://docs.docker.com) for more details.
        
        ### An important note about passwords
        
        The tool uses a simple username/password combination to connect to JIRA. You
        need to ensure this user exists in the remote JIRA instance, and has the
        required permissions.
        
        There are three ways to provide the credentials for JIRA -- in particular, the
        password, which should be kept scret. You should think carefully about which
        approach makes most sense for you.
        
        - The safest option is to not set it in either the configuration file, or as
          a command line option. In this case, you will be prompted to input a
          password (and username, if you didn't set this either) each time the tool
          is run.
        - You can use the `--username` and/or `--password` command line options to set
          credentails when you invoke the `jira-agile-metrics` command. This keeps
          them out of the configuration file, but if you do this in an interactive
          shell that records command history (i.e. virtually all of them), your
          password will likely be stored in plain text in the command history!
        - If you are confident you can keep the configuration file secret, you can
          store them there, under the `Connection` section (see below).
        
        ### What issues should you include?
        
        The most common use case is to calculate metrics for a team using a JIRA issue
        type called something like `Story`, going through a workflow with stages like
        `Backlog`, `Committed`, `Elaboration`, `Build`, `Code review`, `Test`, and `Done`,
        and allowing a set of resolutions like `Completed`, `Withdrawn`, and `Duplicate`.
        
        `jira-agile-metrics` lets you use JIRA JQL syntax to specify which issues you
        are interested in. See the JIRA documentation for more details (or construct a
        search using the JIRA UI and then have JIRA show you the corresponding JQL).
        
        ### Creating a configuration file
        
        Here is an example configuration file for a basic example using the workflow
        above:
        
            # How to connect to JIRA. Can also include `Username` and `Password`
            Connection:
                Domain: https://myjira.atlassian.net # your JIRA instance
        
            # What issues to search for. Uses JQL syntax.
            Query: Project=ABC AND IssueType=Story AND (Resolution IS NULL OR Resolution IN (Completed, Withdrawn))
        
            # The workflow we want to analyse. By convention, the first stage should be
            # the backlog / initial state, and the final stage should indicate the work
            # is done.
            #
            # We map analytics names to JIRA status names. It's possible to collapse
            # multiple JIRA statuses into a single workflow stage, as with `QA` below.
            Workflow: 
                Backlog: Backlog
                Committed: Committed
                Elaboration: Elaboration
                Build: Build
                QA:
                    - Code review
                    - Test
                Done: Done
            
            # What outputs to produce. These are all optional. If an option isn't set
            # the relevant metric will not be produced.
        
            Output:
        
                # CSV files with raw data for input to other tools or further analysis in a spreadsheet
                # If you use .json or .xslx as the extension, you can get JSON data files or Excel
                # spreadsheets instead
        
                Cycle time data: cycletime.csv
                CFD data: cfd.csv
                Scatterplot data: scatterplot.csv
                Histogram data: histogram.csv
                Throughput data: throughput.csv
                Percentiles data: percentiles.csv
        
                # Various charts
        
                Scatterplot chart: scatterplot.png
                Scatterplot chart title: Cycle time scatter plot
                
                Histogram chart: histogram.png
                Histogram chart title: Cycle time histogram
                
                CFD chart: cfd.png
                CFD chart title: Cumulative Flow Diagram
                
                Throughput chart: throughput.png
                Throughput chart title: Throughput trend
                
                Burnup chart: burnup.png
                Burnup chart title: Burn-up
        
                Burnup forecast chart: burnup-forecast.png
                Burnup forecast chart title: Burn-up forecast
                Burnup forecast chart trials: 100 # number of Monte Carlo trials to run to estimate completion date
        
                # Burnup forecast chart throughput window: 60 # Days in the past to use for calculating historical throughput
                # Burnup forecast chart throughput window end: 2018-06-01 # Calculate throughput window to this date (defaults to today)
                # Burnup forecast chart target: 100 # items to complete in total; by default uses the current size of the backlog
                # Burnup forecast chart deadline: 2018-06-01 # deadline date, in ISO format; if not set, no deadline is drawn.
                # Burnup forecast chart deadline confidence: .85 # percentile to use to compare forecast to deadline
                
                WIP chart: wip.png
                WIP chart title: Work in Progress
        
                Ageing WIP chart: ageing-wip.png
                Ageing WIP chart title: Ageing WIP
        
                Net flow chart: net-flow.png
                Net flow chart title: Net flow
        
        Hint: If you prefer to manage your queries as saved filters in JIRA, you can
        use the special JQL syntax of `filter=123`, where `123` is the filter ID.
        
        If you save this file as e.g. `config.yaml`, you can run:
        
            $ jira-agile-metrics config.yaml
        
        This should prompt you for a username and password, and then connect to your
        JIRA instance, fetch the issues matching the query, calculate metrics, and
        write a number of CSV and PNG files to the current working directory (you can
        use the `--output-directory` option to write to another directory).
        
        When testing configuration, it is often helpful to fetch just a small number of
        issues to speed things up. You can either do this by making your query more
        restrictive, or by using the `-n` flag to limit the number of issues fetched:
        
            $ jira-agile-metrics -n 20 config.yaml
        
        If you want more information about what's going on, use the `-v` flag:
        
            $ jira-agile-metrics -v config.yaml
        
        And if you are realy curious:
        
            $ jira-agile-metrics -vv config.yaml
        
        ## Available metrics
        
        `jira-agile-metrics` can produce a number of data files and charts, which can
        be enabled in the `Output` section of the configuration file, or with a
        corresponding command line option.
        
        **Note:** In the configuration file, you can specify output file *names*, but
        not absolute or relative paths. Files will always be written to the current
        working directory. This is to prevent unexpeced behaviour and the potential of
        overwriting other files when configuration files are moved around or used on
        a remote machine. No such restriction applies to output files specified in
        command line arguments.
        
        ### Cycle time details
        
        Details about each ticket and the date it entered each stage of the workflow.
        Both the CSV and JSON versions of this file can be used by the
        [Actionable Agile Analytics](http://actionableagile.com/) tool, which offers
        powerful, interactive analysis of Agile flow.
        
        In the configuration file:
        
            Output:
                Cycle time data: cycletime.csv
        
        You can also use `.json` or `.xlsx` formats.
        
        Note: the "Blocked Days" calculation relies on the "Flagged" feature in JIRA,
        showing the total number of days (rounded up to the nearest whole day) that each
        ticket was flagged as impeded. Impediments raised whilst the ticket is in the
        backlog or done do not count.
        
        ### Cumulative Flow Diagram (CFD)
        
        Raw data for creating a valid Cumulative Flow Diagram, in spreadsheet format,
        and/or an image file of the same. The CFD shows the number of work items in
        each stage of the flow as a stacked area chart, day by day. This allows us to
        visualise WIP, cycle time, and throughput.
        
        ![](./docs/images/cfd.png)
        
        In the configuration file:
        
            Output:
                CFD data: cfd.csv
                CFD chart: cfd.png
                CFD chart title: Cumulative Flow Diagram
        
        You can also use `.json` or `.xlsx` formats for the data file.
        
        To only show the 30 most recent days in the chart:
        
                CFD window: 30
        
        ### Cycle time scatter plot
        
        Raw data for creating a valid Cycle Time scatter plot graph, and/or an image
        file of the same. This chart plots the end-to-end cycle time (excluding time
        spent in the backlog) for each work item against its completion date, and
        overlays quantiles (e.g. 85% of tickets took 18 days or fewer)
        
        ![](./docs/images/scatterplot.png)
        
        In the configuration file:
        
            Output:
                Scatterplot data: scatterplot.csv
                Scatterplot chart: scatterplot.png
                Scatterplot chart title: Cycle time scatter plot
        
        You can also use `.json` or `.xlsx` formats for the data file.
        
        By default, the quantiles used are the 50th, 85th and 95th percentile, but you
        can specify a different list with the `Quantiles` option under `Output`:
        
                Quantiles:
                    - 0.3
                    - 0.5
                    - 0.75
                    - 0.85
                    - 0.95
        
        Note that this option affects all charts that use quantiles.
        
        To get the quantile values (number of day at each quantile) in a data file, use:
        
                Percentiles data: percentiles.csv
        
        To only show the 30 most recent days in the chart:
        
                Scatterplot window: 30
        
        ### Cycle time histogram
        
        This is a different view of the cycle time , calculatd and/or plotted as a
        histogram.
        
        ![](./docs/images/histogram.png)
        
        In the configuration file:
        
            Output:
                Histogram data: histogram.csv
                Histogram chart: histogram.png
                Histogram chart title: Cycle time histogram
        
        You can also use `.json` or `.xlsx` formats for the data file.
        
        This also respects the `Quantiles` option (see above).
        
        To only show the 30 most recent days in the chart:
        
                Histogram window: 30
        
        ### Throughput
        
        Weekly throughput, i.e. the number of items completed week by week. The chart
        also shows a trend line.
        
        ![](./docs/images/throughput.png)
        
        In the configuration file:
        
            Output:
                Throughput data: throughput.csv
                Throughput chart: throughput.png
                Throughput chart title: Throughput trend
        
        You can also use `.json` or `.xlsx` formats for the data file.
        
        To change the frequency from weekly to something else, use:
        
                Throughput frequency: 1D
        
        Here, `1D` means daily. The default is `1W-MON`, which means weekly starting on
        Mondays.
        
        To only show the 6 most recent periods (e.g. weeks) in the chart:
        
                Throughput window: 6
        
        ### WIP box plot
        
        Shows a box plot of WIP, week by week (or some other frequency).
        
        ![](./docs/images/wip.png)
        
        In the configuration file:
        
                WIP chart: wip.png
                WIP chart title: Work in Progress
        
        To change the frequency from weekly to something else, use:
        
                WIP frequency: 1D
        
        Here, `1D` means daily. The default is `1W-MON`, which means weekly starting on
        Mondays.
        
        To only show the 6 most recent periods (e.g. weeks) in the chart:
        
                WIP window: 6
        
        ### Net flow chart
        
        Shows the difference between arrivals and departures week on week. In a
        perfectly stable system, the net flow would be 0.
        
        ![](./docs/images/net-flow.png)
        
        In the configuration file:
        
                Net flow chart: net-flow.png
                Net flow chart title: Net flow
        
        To change the frequency from weekly to something else, use:
        
                Net flow frequency: 1D
        
        Here, `1D` means daily. The default is `1W-MON`, which means weekly starting on
        Mondays.
        
        To only show the 6 most recent periods (e.g. weeks) in the chart:
        
                Net flow window: 6
        
        ### Ageing WIP chart
        
        Shows the cycle time to date for each work item, grouped into the stages of
        the workflow. This can help identify slow-moving tickets.
        
        ![](./docs/images/ageing-wip.png)
        
        In the configuration file:
        
                Ageing WIP chart: ageing-wip.png
                Ageing WIP chart title: Ageing WIP
        
        ### Burn-up chart
        
        A basic Agile burn-up chart, based on a count of items completed and in the
        backlog.
        
        ![](./docs/images/burnup.png)
        
        In the configuration file:
        
                Burnup chart: burnup.png
                Burnup chart title: Burn-up
        
        To only show the 30 most recent days in the chart:
        
                Burnup window: 30
        
        ### Burn-up chart with forecast line
        
        A more advanced version of the burn-up chart, which will run a Monte Carlo
        simulation based on historical throughput to forecast a completion date for
        the scope.
        
        ![](./docs/images/burnup-forecast.png)
        
        The simulation can be calibrated with a series of options to set:
        
        - The number of trials to run. Each trial will be drawn as a hypotehtical
          burn-up to completion.
        - The window of time from which to sample historical throughput. This should
          be representative of the near future, and ideally about 6-12 weeks long.
        - The target to aim for, as a number of stories to have completed. Defaults
          to the size of the backlog, but can be set to an assumed figure.
        - A deadline date, which, if set, can be compared to a forecast at a given
          confidence interval.
        
        In the configuration file:
        
                Burnup forecast chart: burnup-forecast.png
                Burnup forecast chart title: Burn-up forecast
                Burnup forecast chart trials: 100 # number of Monte Carlo trials to run to estimate completion date
        
                Burnup forecast chart throughput window: 60 # Days in the past to use for calculating historical throughput
                Burnup forecast chart throughput window end: 2018-06-01 # Calculate throughput window to this date (defaults to last day of burnup)
                Burnup forecast chart target: 100 # items to complete in total; by default uses the current size of the backlog
                Burnup forecast chart deadline: 2018-06-01 # deadline date, in ISO format; if not set, no deadline is drawn.
                Burnup forecast chart deadline confidence: .85 # percentile to use to compare forecast to deadline
        
        To only show the 30 most recent days in the chart:
        
                Burnup forecast window: 30
        
        ## Impediments
        
        If you use the "Flagged" feature in JIRA to mark (and unmark) tickets as impeded
        when they are blocked, you can produce charts showing the number of impediments
        raised, and the cumulative amount of time tickets have spent being impeded,
        broken down by month and the workflow stage a ticket was in when the impeded
        flag was set. You can also write out the impediment events to a file.
        
        ![](./docs/images/impediments.png)
        
        ![](./docs/images/impediments-days.png)
        
        The charts can be enabled with:
        
            Impediments data: impediments.csv
            Impediments window: 6
            Impediments chart: impediments.png
            Impediments chart title: Number of impediments
            Impediments days chart: impediments-days.png
            Impediments days chart title: Total impeded days
        
        The `Impediments window`, which is optional, can be used to limit the chart to
        showing only the most recent months' data: six in this case.
        
        The `Impediments chart` will count the number of impediment events that were
        active each month, i.e. a ticket was flagged as impeded at some point during
        the month.
        
        The `Impediments days chart` uses the same underlying logic, but instead of
        counting impediments, it sums the number of days of all impediments in each
        month.
        
        Note that:
        
        - Impediments raised against tickets in the backlog or in the "done" column are
          not shown.
        - If a ticket is flagged and then resolved before being unflagged, the impeded
          time is calculated to the resolution date.
        - If a ticket is still flagged at the time the chart is generated, the impeded
          day count will run to today's date.
        - Blocking time is always rounded up to the nearest whole day.
        
        ## Defect density
        
        Three charts for analysing the amount of defects that have been open
        historically, grouped in various ways into stacked bar graphs.
        
        ![](./docs/images/defects-by-priority.png)
        
        ![](./docs/images/defects-by-type.png)
        
        ![](./docs/images/defects-by-environment.png)
        
        These charts all rely on a separate JIRA query:
        
            Defects query: issueType = Bug
        
        Again, you can use the `filter=123` JQL syntax to delegate the query specifics
        to a named filtered.
        
        The three available groupings are:
        
        - Show how many defects remained open each month, grouped by _priority_.
        - Show how many defects remained open each month, grouped by _type_.
        - Show how many defects remained open each month, grouped by _environment_.
        
        They each require you to specify the name of the relevant field, and a chart
        output. You can also optionally specify a list of allowed values for each field,
        which lets you control the order. Finally, you can specify a "window" of how
        many of the most recent months to show (the default is to show all months for
        which there is data). Here is an example that enables all charts, and limits to
        showing the six most recent months in each:
        
            Defects query: issueType = Bug
            Defects window: 6
            Defects priority field: Priority
            Defects priority values:
                - Low
                - Medium
                - High
            Defects type field: Root cause
            Defects type values:
                - Config
                - Data
                - Code
            Defects environment field: Environment
            Defects environment values:
                - SIT
                - UAT
                - PROD
        
            Defects by priority chart: defects-by-priority.png
            Defects by priority chart title: Defects by priority
            Defects by type chart: defects-by-type.png
            Defects by type chart title: Defects by type
            Defects by environment chart: defects-by-environment.png
            Defects by environment chart title: Defects by environment
        
        If you omit any of the chart names, the relevant chart will not be produced. If
        you omit any of the field names, the relevant chart will not be stacked. If you
        omit the values list, all unique values will be shown.
        
        ## Technical debt
        
        Two charts that show the nature and age of recorded (unresolved) technical debt.
        
        ![](./docs/images/tech-debt.png)
        
        ![](./docs/images/tech-debt-age.png)
        
        These require a separate JIRA query. You should also identify the field
        indicating priority:
        
            Debt query: issueType = "Tech debt"
            Debt priority field: Priority
            Debt priority values:
                - Low
                - Medium
                - High
        
        As ever, use `filter=123` to use a named filter instead. If you omit the
        `Debt priority values` option, all unique priority values will be used, in
        alphabetical order.
        
        The first chart shows the open technical debt items each month as a stacked bar
        chart grouped by priority. You can optionally specify a "window" to show only
        a limited number of the most recent months:
        
            Debt window: 3
            Debt chart: tech-debt.png
            Debt chart title: Technical debt
        
        The second chart shows the number of open technical debt items by their current
        age in days, broken down by priority, and stacked into "bins":
        
            Debt age chart: tech-debt-age.png
            Debt age chart title: Technical debt age
            Debt age chart bins:
                - 30
                - 60
                - 90
        
        This will use the age brackets 0-30 days, 31-60 days, 61-90 days, and over 90
        days (which also happens to be the default).
        
        ## Waste (withdrawn items)
        
        This chart shows how many work items are withdrawn or cancelled after work
        has started. It relies on a separate JIRA query, and assumes that withdrawn
        work items are all "resolved" in JIRA. Moreover, it assumes that these work
        items follow the same workflow as that used for the other charts and files,
        i.e. as mapped in the `Workflow` section of the configuration file.
        
        ![](./docs/images/waste.png)
        
        Here is an example:
        
            Waste query: issueType = Story AND resolution IN (Withdrawn, Invalid)
            Waste window: 10
            Waste frequency: 2W-WED
            Waste chart: waste.png
            Waste chart title: Waste
        
        This will show withdrawn items broken down by the period in which they were
        withdrawn for the the 10 most recent periods. The default period length is
        monthly, but here we have set it to `2W-WED`, which means a two-week period
        starting on a Wednesday. `Waste window` and `Waste frequency` are both
        optional.
        
        ## More details about the configuration file format
        
        The configuration file is written in YAML format. If you are unfamiliar with
        YAML, know that:
        
        * Comments start with `#`
        * Sections are defined with a name followed by a colon, and then an indented
          block underneath. `Connection`, `Output`, `Workflow` and `Attributes` area
          all sections in the example above.
        * Indentation has to use spaces, not tabs!
        * Single values can be set using `Key: value` pairs. For example,
          `Burnup chart: burnup.png` above sets the key `Burnup chart` to the value
          `burnup.png`.
        * Lists of values can be set by indenting a new block and placing a `-` in front
          of each list value. In the example above, the `QA` list contains
          the values `Code review` and `Test`.
        
        The sections for `Workflow` is required. Additionally, you must either specfiy a
        single `Query`, or a block of `Queries` (see below). Connection details must
        be set either in the `Connection` file or as command line arguments.
        
        Under `Workflow`, at least two steps are required. Specify the steps in order.
        You may either specify a single workflow value or a list (as shown for `QA`
        above), in which case multiple JIRA statuses will be collapsed into a single
        state for analytics purposes.
        
        The file, and values for things like workflow statuses and attributes, are case
        insensitive.
        
        ### Extracting additional attributes
        
        You may want to add additional fields to the cycle time output data. Use an
        `Attributes` block to do this:
        
            Attributes:
                Priority: Priority
                Release: Fix version/s
                Team: Team name
        
        Here, three additional columns will be added: `Priority`, `Release` and `Team`,
        corresponding to the JIRA fields `Priority`, `Fix version/s` and `Team name`,
        respectively.
        
        When specifying attributes, use the *name* of the field (as rendered on screen
        in JIRA), not its id (as you might do in JQL), so e.g. use `Component/s` not
        `components`.
        
        The attributes `Type` (issue type), `Status` and `Resolution` are always
        included.
        
        ### Multi-valued fields
        
        Some fields in JIRA can contain multiple values, e.g. `fixVersion`. By default,
        the extractor will use the first value in such a field if one is specified in
        the `Attributes` block. However, you may want to extract only specific values.
        
        To do so, add a block like the following::
        
            Attributes:
                Release: Fix version/s
        
            Known values:
                Release:
                    - "R01"
                    - "R02"
                    - "R03"
        
        The extractor will pick the first "known value" found for the field. If none of
        the known values match, the cell will be empty.
        
        ### Combining multiple queries
        
        If it is difficult to construct a single set of criteria that returns all
        required issues, multiple queries can be added into a `Queries` block, like so:
        
            Queries:
                Attribute: Team
                Criteria:
                    - Value: Team 1
                      JQL: (filter=123)
        
                    - Value: Team 2
                      JQL: (filter=124)
        
        In this example, two queries will be run, based on the two filters `123` and
        `124` (you can use any valid JQL).
        
        In the cycle time output, a new column called `Team` will be added, as specified
        by the `Attribute` field under `Queries`. For all items returned by
        the first query, the value will be `Team 1` as per the `Value` field, and for
        all items returned by the second query, it will be `Team 2`.
        
        ## Troubleshooting
        
        * If Excel complains about a `SYLK` format error, ignore it. Click OK. See
          https://support.microsoft.com/en-us/kb/215591.
        * JIRA error messages may be printed out as HTML in the console. The error is
          in there somewhere, but may be difficult to see. Most likely, this is either
          an authentication failure (incorrect username/password or blocked account),
          or an error in the `Query` option resulting in invalid JQL.
        * If you aren't getting the issues you expected to see, use the `-v` option to
          see the JQL being sent to JIRA. Paste this into the JIRA issue filter search
          box ("Advanced mode") to see how JIRA evaluates it.
        * Old workflow states can still be part of an issue's history after a workflow
          has been modified. Use the `-v` option to find out about workflow states that
          haven't been mapped.
        * Excel sometimes picks funny formats for data in CSV files. Just set them to
          whatever makes sense.
        * If you are on a Mac and you get an error about Python not being installed as
          a framework, try to create a file `~/.matplotlib/matplotlibrc` with the
          following contents:
        
            backend : Agg
        
        * To install the charting dependencies on a Mac, you might need to install a
          `gfortran` compiler for `scipy`. Use [Homebrew](http://brew.sh) and install the
          `gcc` brew.
        
        ## Output settings reference
        
        The following options can be set in the `Output:` section of the configuration
        file.
        
        ### General options
        
        These options affect multiple charts and files.
        
        - `Quantiles: <list>` – Quantiles to use when calculating percentiles.
        - `Backlog column: <name>` --Name of the backlog column. Defaults to the first column.
        - `Committed column: <name>` – Name of the column from which work is considered
           committed. Defaults to the second column.
        - `Final column: <name>` – Name of the final 'work' column. Defaults to the
           penultimate column.
        - `Done column: <name>` – Name of the 'done' column. Defaults to the last column.
        
        ### Data files
        
        These options name data files to write. Use an extension of `.csv`, `.xlsx`, or
        `.json` according to the required file format.
        
        - `Cycle time data: <filename>.[csv,xlsx,json]` – Output file suitable for
           processing Actionable Agile. Contains all issues described by the
           configuration file, metadata, and dates of entry to each state in the cycle.
        - `CFD data: <filename>.[csv,xlsx,json]` – Calculate data to draw a Cumulative
           Flow Diagram and write to file. Hint: Plot as a (non-stacked) area chart.
        - `Scatterplot data: <filename>.[csv,xlsx,json]` – Calculate data to draw a
           cycle time scatter plot and write to file. Hint: Plot as a scatter chart.
        - `Histogram data: <filename>.[csv,xlsx,json]` – Calculate data to draw a cycle
           time histogram and write to file. Hint: Plot as a column chart.
        - `Throughput data: <filename>.[csv,xlsx,json]` – Calculate daily throughput
           data and write to file. Hint: Plot as a column chart. Respects the
           `Throughput frequency` setting (see below).
        - `Percentiles data: <filename>.[csv,xlsx,json]` – Calculate cycle time
           percentiles and write to file.
        - `Impediments data: <filename>.[csv,xlsx,json]` – Output impediment start and
           end dates against tickets.
        
        ### Scatterplot chart
        
        - `Scatterplot window: <number>` – Number of recent days to show in scatterplot.
           Defaults to showing all data.
        - `Scatterplot chart: <filename>.png` – Draw cycle time scatter plot.
        - `Scatterplot chart title: <title>` – Title for cycle time
           scatter plot.
        
        ### Histogram chart
        
        - `Histogram window: <number>` – Number of recent days to show in histogram.
           Defaults to showing all data.
        - `Histogram chart: <filename>.png` – Draw cycle time histogram.
        - `Histogram chart title: <title>` – Title for cycle time
           histogram.
        
        ### Cumulative Flow Diagram
        
        - `CFD window: <number>` – Number of recent periods to show in the CFD.
           Defaults to showing all periods.
        - `CFD chart: <filename>.png` – Draw Cumulative Flow Diagram.
        - `CFD chart title: <title>` – Title for the CFD.
        
        ### Throughput chart
        
        - `Throughput frequency: <freq>` – Interval to use for calculating frequency,
           e.g. 1D for daily or 1W for weekly.
        - `Throughput window: <number>` – Number of recent periods to show in throughput chart.
           Defaults to showing all periods.
        - `Throughput chart: <filename>.png` – Draw weekly throughput chart with trend
          line.
        - `Throughput chart title: <title>` – Title for throughput chart.
        
        ### Burnup chart
        
        - `Burnup window: <number>` – Number of recent periods to show in burnup.
           Defaults to showing all periods.
        - `Burnup chart: <filename>.png` – Draw simple burn-up chart.
        - `Burnup-chart-title <title>` – Title for burn-up charts_scatterplot.
        
        ### Burnup forecast chart
        
        - `Burnup forecast window: <number>` – Number of recent periods to show in the
           burnup forecast chart. Defaults to showing all periods.
        - `Burnup forecast chart: <filename>.png` – Draw burn-up chart with Monte Carlo
           simulation forecast to completion.
        - `Burnup forecast chart title: <title>` – Title for burn-up forecast chart.
        - `Burnup forecast chart target: <number>` – Target completion scope for
           forecast. Defaults to current size of backlog.
        - `Burnup forecast chart deadline: <date>` – Deadline date for completion of
           backlog. If set, it will be shown on the chart, and the forecast delta will
           also be shown. Use ISO date format, e.g. `2018-01-02` for January 2nd 2018.
        - `Burnup forecast chart deadline confidence: <number>` – Quantile to use when
           comparing deadline to forecast. Use a fraction, e.g. `0.85`.
        - `Burnup forecast chart trials: <number>` – Number of iterations in Monte
           Carlo simulation.
        - `Burnup forecast chart throughput window: <number>` – How many days in the
           past to use for calculating throughput.
        - `Burnup forecast chart throughput window end: <date>` – By default, the
           throughput window runs to today's date. Use this option to set an alternative
           end date for the window. Use ISO date format, e.g. `2018-01-02` for January
           2nd 2018.
        
        ### WIP chart
        
        - `WIP frequency: <freq>` – Frequency interval for WIP chart. `1W-Mon`
           means 1 week, starting Mondays.
        - `WIP window: <number>` – Number of recent periods to show in WIP chart.
           Defaults to showing all periods.
        - `WIP chart: <filename>.png` –  Draw weekly WIP box plot.
        - `WIP chart title: <title>` – Title for WIP chart
        
        ### Ageing WIP chart
        
        - `Ageing WIP chart: <filename>.png` – Draw current ageing WIP chart.
        - `Ageing WIP chart title: <title>` – Title for ageing WIP chart.
        
        ### Net flow chart
        
        - `Net flow frequency: <freq>` – Frequency interval for net flow chart.
          `1W-Mon` means 1 week, starting Mondays.
        - `Net flow window: <number>` – Number of recent periods to show in net flow
           chart. Defaults to showing all periods.
        - `Net flow chart: <filename>.png` – Draw weekly net flow bar chart.
        - `Net flow chart title: <title>` – Title for net flow bar chart.
        
        ## Impediments chart
        
        - `Impediments window: <number>` – How many months to show.
        - `Impediments chart: <filename>.png` – Draw a bar chart of the number of
          active impediments during each month, stacked by the ticket status at the
          time the impediment was raised.
        - `Impediments chart title: <title>` – Title for the impediments chart.
        - `Impediments days chart: <filename>.png` – Draw a bar chart of the total
           number of days of all the impediments active during each month, stacked by
           the ticket status at the time each impediment was raised.
        - `Impediments days chart title: <title>` – Title for the impediments days
           chart.
        
        ### Defect density charts
        
        - `Defects query: <query>` – JQL query used to identify defects.
        - `Defects window: <number>` – How many months to show.
        - `Defects priority field: <fieldname>` – Name of field identifying
           defect priority.
        - `Defects priority values: <list>` – List of valid values, in order,
           for defect priorities.
        - `Defects type field: <fieldname>` – Name of field identifying defect
           type.
        - `Defects type values: <list>` – List of valid values, in order, for
           defect values.
        - `Defects environment field: <fieldname>` – Name of field identifying
           the environment in which a defect was discovered.
        - `Defects environment values: <list>` – List of valid values, in
           order, for defect environments.
        
        - `Defects by priority chart: <filename>.png` – Draw stacked bar chart of
           defects grouped by priority over time.
        - `defects-by priority chart title: <title>` – Title for defects-by-priority
           chart.
        
        - `Defects by type chart: <filename>.png` – Draw stacked bar chart of defects
           grouped by type over time.
        - `Defects by type chart title: <title>` – Title for defects-by-type chart.
        
        - `Defects by environment chart: <filename>.png` – Draw stacked bar chart of
           defects grouped by environment over time.
        - `Defects by environment chart title: <title>` – Title for defects-by-
           environment chart.
        
        ### Debt density chart
        
        - `Debt query: <query>` – JQL query used to identify technical debt items.
        - `Debt window: <number>` – How many months to show in the debt chart. Defaults
           to showing all months for which there is data.
        - `Debt priority field: <fieldname>` – Name of field identifying technical debt
           item priority.
        - `Debt priority values: <list>` – List of valid values, in order, for
           technical debt item priorities.
        
        - `Debt chart: <filename>.png` – Draw a stacked bar chart of technical debt
           grouped by priority over time.
        - `Debt chart title: <title>` – Title for the technical debt chart.
        
        - `Debt age chart: <filename>.png` – Draw a stacked bar chart of technical debt
           grouped by priority by age.
        - `Debt age chart title: <title>` – Title for the technical debt age chart.
        - `Debt age chart bins: <list>` – List of bins for bracketing the ages shown.
           Defaults to `30`, `60`, and `90`, which will group ages into `0-30 days`,
           `31-60 days`, `61-90 days` and `91 days or more`.
        
        ### Waste chart
        
        - `Waste query: <query>` – JQL query used to identify waste items, e.g.
           those withdrawn after work has begun.
        - `Waste frequency: <freq>` – Frequency to group waste chart by. Defaults to
           month start (`MS`). Use e.g. `2W-WED` to group by fortnight starting
           Wednesday.
        - `Waste window: <number>` – How many months to show.
        - `Waste chart: <filename>.png` – Draw a stacked bar chart of wasted items,
           grouped by last non-resolved status.
        - `Waste chart title: <title>` – Title for the waste chart.
        
        ## Changelog
        
        ### 0.7
        
        * Turn throughput chart into a line chart
        
        ### 0.6
        
        * Don't log every list value resolution at debug
        
        ### 0.5
        
        * Added batch mode docker image
        
        ### 0.4
        
        * Added impediments charts
        
        ### 0.3
        
        * Added debt, defects, and waste charts.
        * Added `window` options to most charts.
        
        ### 0.2
        
        * Added `--output-directory` option.
        
        ### 0.1
        
        * Forked from `jira-agile-metrics`
        